Case Studies

Company: Sheet Metal Fabricators

KWH Cost

Current Use: 483839 €62,899

Solution Provided: 128053 €16,647

Annual Project Energy Savings 355786 €46,253

Life Project Savings: 1778930 €231,265

Incentive Received €17,789

Cost of Materials €30,472

Net Investment: €12,683

ROI: 3 Months

Company: Hotel Leisure and Conference Centre

KWH Cost

Current Use: 228585 €34,996

Solution Provided: 59276 €9,075

Annual Project Energy Savings 169309 €25,921

Life Project Savings: 846545 €129,605

Incentive Received €8,465

Cost of Materials €38,036

Net Investment: €29,571

ROI: 13 Months

Company: Industrial Engineering

KWH Cost

Current Use: 887080 €98,886

Solution Provided: 292028 €32,507

Annual Project Energy Savings 595052 €66,379

Life Project Savings: 2975260 €331,895

Incentive Received €29,753

Cost of Materials €81,353

Net Investment: €51,600

ROI: 9 Months

1 view0 comments

Recent Posts

See All

Get a 30% Grant for your Lighting Upgrade!

StartFragment SME Supports for Lighting Upgrades Get a 30% Grant for your lighting Upgrade! The SEAI in their efforts to help SMEs reduce their energy costs have just announced a Smart Lighting Grant

Comments


bottom of page